Are you in the middle of an outage right now?Call us directly: +49 2161 999 52 29. Within a few minutes on the phone we can establish what is feasible at your site – emergencies around the clock.
The first 60 minutes
The first hour after a failure sets the course for the entire recovery. Experience shows that most of the time is lost not through missing technology, but through unclear responsibilities and people acting in parallel on their own.
- Protect people. In the event of fire, smoke or water ingress the rule is: clear the room, trigger the emergency response chain, no rescue attempts for hardware. Servers are replaceable.
- Narrow down the cause. Is power, cooling, network or the building envelope affected? That answer decides whether replacement infrastructure can be operated at the same site at all.
- Shut down in a controlled way. If the cooling fails, depending on room size and occupancy there are often only a few minutes before critical temperatures are reached. Shut down systems that are not strictly needed in an orderly manner – this prevents hardware damage and data inconsistencies.
- Set up a crisis team. One person decides, one person communicates internally and externally, one person documents times and actions. The documentation is later relevant for insurers and auditors.
- Request replacement capacity in parallel. The most common and most expensive mistake: waiting for the loss adjuster's report before sourcing a replacement. Enquiring in parallel costs you nothing – waiting costs days.
Why a parallel enquiry costs nothingA feasibility check is non-binding. If the damage assessment shows that the server room will be usable again in three days, the enquiry is simply not pursued. If it shows the opposite, you have already gained a day.
Which failures call for a replacement solution
Not every incident creates a need for replacement capacity. The following classification helps you judge whether a mobile solution makes sense.
| Scenario | Typical downtime | Replacement data center worthwhile? |
|---|---|---|
| UPS failure with the mains supply intact | hours to 2 days | rarely – repair is usually faster |
| Cooling system failure | 1 day to several weeks | often – including as emergency cooling only |
| Water damage in the server room | weeks to months | yes – the room is usually unusable for some time |
| Fire or fire damage | months | yes – including the remediation phase |
| Building damage / access prohibited | weeks to months | yes – a change of site is required |
| Grid connection permanently overloaded | months (network reinforcement) | yes – as a bridge until the upgrade |
The 48-hour sequence in detail
The sequence below describes the standard case with a standard system available and a suitable site. It is not a guarantee – but it is a realistic benchmark for what is organisationally possible.
- Hours 0–2 Initial call and feasibility
Capturing IT load, site, available connected load and target date by phone. The result is a clear statement of whether delivery is possible and in what configuration.
- Hours 2–6 Configuration, quote, approval
Defining cooling, UPS, a backup generator if required, and connectivity. In parallel, access routes and the crane standing area are checked – ideally from photos or a satellite image of the site.
- Hours 6–24 Preparation and transport
The system is prepared for deployment, loaded and driven to the site. For larger systems, special permits and the crane are organised in parallel.
- Hours 24–36 Positioning and connection
Setting down on the prepared footprint, alignment, connection to power and network, commissioning of cooling, UPS and fire protection.
- Hours 36–48 Function testing and handover
Testing of all systems, connection to remote monitoring, handover to your team. From this point on, racks can be populated and systems started up.
An emergency? We check feasibility on the phone straight away
Have your IT load, site and available connected load to hand – then you get a reliable answer in the first call instead of a promise to call back.
Where time gets lost
In practice the critical path almost never runs through the data center itself, but through site preparation. These three points cause most of the delays:
The power connection
If there is not enough connected load available at the replacement site, either the supply cable has to be upgraded or a backup generator has to be planned in. Upgrading involves the network operator and normally takes weeks. A backup generator is more expensive to run, but immediately available – and it makes the schedule independent of network reinforcement work.
The footprint
What is needed is a sufficiently level surface that carries the load, plus access for lorry and crane. Lawns, underground car park decks and tight courtyards are the classic problem cases. A photo of the intended area and the access route answers more questions in the first call than any written description.
Internal decision paths
Approvals, procurement rules and insurance queries regularly cost more time in an emergency than transport and installation combined. Defining an escalation and approval procedure for emergencies in advance saves exactly those hours.
The 5 details that speed everything up
With this information, a reliable feasibility statement is usually possible within a few hours:
- IT load required in kW. What absolutely has to keep running? A fraction of the original capacity is often enough at first to cover the business-critical systems.
- Available connected load. What capacity is actually available at the replacement site, and how far away is the transfer point?
- Footprint and access. Address, ground surface, approximate dimensions, access width – ideally with a photo.
- Network connectivity. Is fibre usable on site, or is a link via 5G/LTE or microwave radio needed?
- Target date. From when do the systems have to be running again? This determines which compromises in the configuration make sense.
Being prepared before it happens
The most effective lever for short recovery times sits before the event. Three measures with a very good effort-to-benefit ratio:
- Record a site profile. Document the connected load, possible footprints, the access situation and contacts once. That removes the entire clarification phase when it matters.
- Define a minimum configuration. Which systems really have to run first? Settle it in advance and you will not be debating it under time pressure.
- Clarify the approval route for emergencies. Who may place an order in an emergency, and up to what amount, without further sign-off?
How the costs of such a replacement solution are made up is covered in the article Renting a mobile data center: the factors that determine the price.
Frequently asked questions
How quickly can a mobile data center really be on site in an emergency?
With a standard system available and a suitable site, delivery in under 48 hours is possible – including positioning, connection and commissioning. The decisive factor is less the container than the site preparation: footprint, power connection and network connectivity set the schedule.
What is the most common cause of delay in an emergency?
The electrical connection. If there is not enough capacity available at the site, either the supply cable has to be upgraded or a backup generator has to be planned in. Both can be accelerated if the available connected load is known at the time of the first enquiry.
Can a mobile data center run without a permanent power connection?
Yes. For emergencies and sites without a sufficient connection, a backup generator can be supplied to bridge operation until the regular supply is in place. That is more expensive to run, but it makes the replacement infrastructure independent of the network operator's construction schedule.
Which details speed up an emergency request the most?
Five details: the IT load required in kW, the connected load available at the site, the condition of and access to the footprint, the type of network connectivity, and the point from which the systems have to be running again. With that information, a reliable feasibility statement is usually possible within a few hours.
Is an emergency agreement worth putting in place in advance?
For companies with critical processes, yes. If site data, connection values and configuration are recorded in advance, the entire clarification phase disappears when it matters – experience shows that this saves half a day to a full day.
Last updated on